SolarWay – Energy Solutions implemented on behalf of the Energy Community of Kalamata Messinia, a 1 MW photovoltaic power plant.
It is the first photovoltaic power plant connected in Messinia, after 8 years!
Both the licensing and the supply, implementation, installation and connection to the HEDNO network was done entirely by SolarWay. The photovoltaic power plant is located in the area of Hatzi, Messinia.
After 8 years, when the implementation of photovoltaic power plants was frozen throughout the Peloponnese, SolarWay implemented the first photovoltaic power plant connected to Messinia, inaugurating the new era. The 1 MW photovoltaic power plant was implemented on behalf of the Energy Community of Kalamata, Messinia.
Both the licensing and the supply, implementation, installation and connection to the HEDNO network was done entirely by SolarWay.
The construction of the photovoltaic power plant was done by SolarWay in a record time of less than a month in April 2021, while already in June 2021, the photovoltaic park produces “green” electricity.
The photovoltaic power plant is located in the area of Hatzi, Messinia.
The photovoltaic power plant consists of:
- 1886 bifacial photovoltaic panels of Trina Solar type Vertex TSM – DEG19C.20 530 Wp
- 5 SUN2000-185KTL – H1 Inverters and one SUN2000-105KTL – H1 from Huawei Technologies Co.,
- Support bases of the Greek “Emmanuel SA”
- Medium Voltage Subpower plant 1000 KVA of the Hellenic “Seller Hellas SA”
The design of the photovoltaic system follows the standards IEC 62446-1: 2016 and IEC 62446-2: 2020 «Photovoltaic (PV) systems – Requirements for testing, documentation and maintenance – Part 1: Grid connected systems – Documentation, commissioning tests and inspection and Part 2: Grid connected systems – Maintenance of PV systems »
The photovoltaic system has been inspected according to IEC 62446-1: 2016 and is in compliance with the requirements of IEC 60364-6.