Another 12 photovoltaic systems were successfully activated by SolarWay in March and April 2012.

Specifically, the following systems were activated and put into production:

On 02/03/2012, a photovoltaic park of 99.88 kW power was activated in a stadium in the area of ​​Ano Ampelokipoi, Messinia.
On 03/03/2012, a 9.8 kW photovoltaic system was activated on a roof in Kalamata.
On 19/03/2012, a 9.87 kW photovoltaic system was activated on a roof in the area of ​​Leika in Kalamata.
On 19/03/2012, a 9.87 kW photovoltaic system was activated on a roof in Kalamata.
On 26/03/2012, a 9.87 kW photovoltaic system was activated on a roof in Kalamata.
On 03/26/2012, a 9.8 kW photovoltaic system was activated on a roof on the beach of Kalamata.
On 03/26/2012, a 9.89 kW photovoltaic system was activated on a roof in Giannitsanika in Kalamata.
On 4/04/2012, a 9.8 kW photovoltaic system was activated on a roof in the area of ​​Agia Triada, Kalamata.
On 06/04/2012, a photovoltaic system of 10.0 kW power was activated on a roof in Kalamata.
On 09/04/2012, a 9.87 kW photovoltaic system was activated on a roof in Iklaina, Messinia.
On 22/04/2012, a photovoltaic system of 9.87 kW was activated on a roof in the center of Kalamata.
On 04/23/2012, a 9.8 kW photovoltaic system was activated on a roof in Piperitsa, Messinia.